Data centre and server room electrical work in Calgary

A server room is a small, continuous load that must never drop. A data hall is the same problem at utility scale. The electrical design follows from two questions: how much power, and what happens when any one piece fails.

Drawing E-209Checked 2026-09-258 min read14 sources

1,200 MWAESO interim large-load limit to 2028, fully allocated: 970 MW to GLDC and 230 MW to Keephills11
90%ENMAX demand ratchet: billing demand is at least 90% of the highest kVA peak in the last 365 days5
150 kVAPeak that, registered twice in 365 days, moves an ENMAX site to D310 Large Commercial5

CCT 01From a server closet to a data hall

“Data centre” covers facilities that differ by orders of magnitude, and the electrical questions change with scale.

  • Server closet or network room. A few racks inside an office or clinic, often on the tenant’s panel. The issues are a dedicated circuit or two, a small UPS, cooling, and whether the landlord’s electrical room can supply more. It is usually part of a tenant improvement.
  • Dedicated computer room. A room with its own distribution, a larger UPS, often a standby generator and precision cooling. Now the building service, the transfer equipment and the maintenance strategy all matter.
  • Colocation suite or data hall. Many racks, redundant utility and generator paths, and a load large enough that the utility plans for it. The power supply is a project of its own, sometimes years ahead of the building.

At every scale the load has two parts: the IT equipment itself and the cooling that removes its heat. Every kilowatt the servers draw becomes heat the mechanical system must reject, so the electrical capacity has to carry both. Size the service on a qualified load calculation that includes cooling, not on the IT figure alone.

CCT 02The critical power chain, and where redundancy goes

Critical power runs through a chain: the utility service, the main switchgear, an automatic transfer switch to the generator, the UPS, then distribution to power distribution units and the rack power strips. Each link can fail or need maintenance, and the design decides which failures the room survives.

Redundancy is described in plain notation rather than numbers of nines:

  • N is exactly enough capacity for the load. Any failure or maintenance outage drops the load.
  • N+1 adds one spare module, such as one more UPS module or generator than the load needs. One unit can fail or be serviced without an outage, but the shared parts (a single bus, a single transfer switch) remain single points of failure.
  • 2N is two complete, independent paths, typically an A and a B feed to dual-corded equipment. Either path can be shut down for maintenance.
  • Concurrent maintainability means every component can be taken out of service for planned work without dropping the load. It is a test of the whole design, including bypasses and cable routes, not of the UPS alone.

Be wary of any uptime percentage attached to a design category. Availability depends on the equipment, the maintenance and the people as much as on the diagram. Ask the designer instead to walk through a list of failure and maintenance scenarios and show what stays energized in each.

CCT 03UPS, batteries and standby generators

The UPS bridges the gap between a utility failure and the generator taking load, and it conditions power the rest of the time. Its battery runtime should cover generator start, transfer and a margin for a failed first start, and should be set by the design, not by habit. Plan for:

  • Bypass arrangements. An internal static bypass and an external maintenance bypass, so the UPS can be serviced or replaced without shutting down the room.
  • Batteries. Chemistry, room ventilation and fire separation, replacement cycles and monitoring are design decisions with code and insurer implications.
  • Power quality. UPS and IT loads affect the building’s power factor and harmonics. ENMAX requires customers to keep power factor at 90% or better, and can require corrective equipment at the customer’s expense.1

The standby generator and its automatic transfer switch carry the load through longer outages. Keep the IT standby system distinct from any life-safety emergency power: they are treated differently under the electrical code, and life-safety loads have priority. Calgary Fire Department’s guidance cites CSA C282-15 for emergency generator maintenance,2 while CSA’s current edition is C282:24,3 so specify the edition the fire code references. Calgary’s January design temperature is −30 °C,4 which makes block heaters, fuel choice, enclosure heating and cold-start testing part of the design. The generator and ATS cost guide covers what drives the price.

An electrician in arc-rated coveralls and a hard hat walking a long lineup of grey commercial switchgear with glowing indicator lamps

CCT 04How ENMAX sees a server room: kVA, the ratchet and large load

A data load runs day and night, which changes how the utility bills it. ENMAX Power bills commercial demand in kVA, not kW. Billing demand is the greatest of metered, ratchet or contract demand, and the ratchet is 90% of the highest kVA demand in the last 365 days.5 One peak during commissioning or a cooling failure can set the demand bill for a year, so plan load bank tests and cut-overs with the meter in mind.

  • Rate class. A site moves to D310 Large Commercial once it registers a monthly peak above 150 kVA twice in 365 days, at secondary voltage.5 D310 carries a service charge of $26.041806 a day plus per-kVA facilities and demand charges.5
  • Metering. ENMAX installs interval meters at new sites planned at 150 kVA or more.1 ENMAX requires a CT request form and checklist for services over 200 A,6 covered in the CT metering guide.
  • Large load. ENMAX treats projects above 1 MVA, or 720 kVA in the downtown core, as a large-load project type in its intake process.7 Raise these early; capacity at the location can decide the site.
  • Investment. Medium and large commercial customers can take ENMAX investment of $367 per kVA of minimum contract demand on a 15-year agreement, up to 80% of anticipated maximum demand.8 That is a credit against ENMAX’s cost, paired with a long commitment to pay for the demand.

Energy is a separate purchase. A site whose annual consumption is forecast under 250 MWh is eligible for the Rate of Last Resort;9 as arithmetic only, a hypothetical load drawing a steady 30 kW all year uses 30 × 8,760 = 262,800 kWh, just over that line. The ENMAX commercial connection guide covers the process step by step.

CCT 05Alberta’s large-load limits for data centres

At the scale of hyperscale and AI data centres, the constraint is the provincial grid, not the building. On June 4, 2025 the Alberta Electric System Operator set an interim limit allowing up to 1,200 MW of large load projects, such as data centres, to connect between then and 2028.10 The interim approach applied to load projects of 75 MW or more.10

Phase 1 is complete. All 1,200 MW was allocated to two projects, the GLDC load (970 MW) and Keephills Data Centre Phase I (230 MW), and other requests move to Phase 2.11 Demand has not slowed: the Government of Alberta reports about 19,565 MW of new data centre load requesting connection on the AESO list of July 30, 2026.12

The province has also changed the order of the queue. According to the Government of Alberta’s summary, the Data Centre Regulation, in force since June 2026, puts projects that pair their demand with dedicated new generation or storage at the front of the connection line.12 This page relies on that summary; read the regulation itself before relying on it for a project.

Scale check

These numbers describe projects of tens or hundreds of megawatts. A Calgary server room, computer room or colocation suite is far smaller and is connected through the wire owner’s normal process, which in Calgary is ENMAX Power. Outside ENMAX’s area, confirm the wire owner first.

CCT 06Permits, drawings and commissioning

Critical power work is permitted and inspected like any other commercial electrical work, with more paperwork because the equipment is larger.

  • Drawings at 600 A and above. Calgary requires plans for new construction or service upgrades of 600 A and higher, including all high-voltage installations.13 The single-line diagram must show fault current at every overcurrent device and any series-rated combinations.13
  • Separate permits. Base-building work and tenant-space work take separate electrical permits in Calgary,13 which matters when a colocation tenant fits out a suite in a landlord’s building.
  • Fire alarm and suppression interfaces. Altering or installing a fire alarm needs both an electrical and a building permit,13 and suppression releases and emergency power-off controls have to be coordinated with it.
  • Code edition. Installations permitted now follow the 2024 Canadian Electrical Code, CSA C22.1-24.14

Commissioning is where redundancy is proved. Beyond each component’s start-up, an integrated systems test pulls the utility and watches the transfer, the UPS and the generators carry a real or load-bank load. Write the test scenarios into the contract, agree who witnesses them, and book the utility and the load bank with the demand ratchet in mind.

CCT 07Data centre scopes and the services they draw on

Typical data centre and server room scopes mapped to services
ScopeWhere it sitsService
Server closet circuits, small UPS, cooling feed in a suiteTenant fit-outTenant improvements
More capacity for a computer room or data hallBase building and ENMAXCommercial service upgrades
Main switchgear, transformers, A and B distributionElectrical roomSwitchgear & transformers
Standby generator, transfer switches, load banksSite and electrical roomGenerators & transfer switches
Infrared scans, breaker testing, planned shutdownsOperationsPreventive electrical maintenance
Short-circuit, coordination and arc flash labelsEngineeringArc flash studies
Fire alarm and suppression interfacesLife safetyFire alarm systems

Most server room work in Calgary starts in the first row and grows into the second. Before a room outgrows its panel, check the building’s recorded peak against its service rating; the service capacity calculator below does the arithmetic. Continuous loads also change maintenance: equipment that never turns off can only be serviced if the design allows it, which is the case for building concurrent maintainability in from the start.

Questions people ask

What are the electrical requirements for a server room?

At minimum: dedicated circuits sized for the IT and cooling load, a UPS sized for the load and the time needed to reach generator power or a clean shutdown, grounding and bonding to the code, and capacity in the building service. Larger rooms add a standby generator and transfer switch, redundant distribution and monitoring. In Calgary the work needs an electrical permit, and services of 600 A and above need drawings.13

What does N+1 mean for a UPS or generator?

N is the capacity the load needs; N+1 adds one spare module, so one unit can fail or be serviced without dropping the load. It is not the same as 2N, which provides two independent paths. Shared components in an N+1 design, such as a single bus or transfer switch, can still be single points of failure.

How much power can new data centres get in Alberta?

The AESO’s interim limit allowed up to 1,200 MW of large load to connect to 2028, and it has been fully allocated: 970 MW to GLDC and 230 MW to Keephills.11 About 19,565 MW of data centre load was requesting connection as of July 30, 2026.12 These figures change quarterly.

How does ENMAX bill a data centre’s demand?

In kVA, per day. Billing demand is the greatest of metered, ratchet or contract demand, and the ratchet is 90% of the highest kVA peak in the previous 365 days.5 A site that peaks above 150 kVA twice in 365 days moves to D310.5 Energy, the local access fee and riders are billed separately.

What is a large load for ENMAX?

ENMAX lists large load as a project type for projects above 1 MVA, or 720 kVA in the downtown core.7 Start the conversation with ENMAX while the site and design can still change, because capacity at the location affects cost and feasibility.

Sources

  1. ENMAX Power Corporation Distribution Tariff - Customer Terms and ConditionsENMAX Power Corporation · Effective January 1, 2026; retrieved 2026-09-25
  2. Fire Safety Maintenance Requirements (Calgary Fire Department Inspections)The City of Calgary (Calgary Fire Department) · Latest revision May 1, 2024 (NFC(AE) 2023); retrieved 2026-09-25
  3. CSA C282:24 Emergency electrical power supply for buildings (store listing)CSA Group · retrieved 2026-09-25
  4. National Building Code - 2023 Alberta Edition, Volume 1, Division B, Appendix C, Table C-2 Climatic Design Data for Selected Locations in AlbertaAlberta Municipal Affairs / National Research Council of Canada · 2023 Alberta Edition, second printing incl. revisions and errata released April 2026
  5. ENMAX Power Corporation Distribution Tariff Rate Schedule - rates in effect as of July 1, 2026ENMAX Power Corporation · Rates in effect as of July 1, 2026 (DAS/SAS rates per AUC Decision 30299-D01-2025, effective January 1, 2026); retrieved 2026-09-25
  6. Get the power flowingENMAX Power Corporation · retrieved 2026-09-25
  7. Start a projectENMAX Power · retrieved 2026-09-27
  8. ENMAX Power Corporation Distribution Tariff, Terms and Conditions Investment Level ScheduleENMAX Power Corporation · Effective January 1, 2026 (applies January 1 to December 31, 2026)
  9. Rate of Last Resort Regulation, Alta Reg 262/2005 (office consolidation)Alberta King's Printer · Consolidation current as of March 27, 2026 (amendments to AR 63/2026); retrieved 2026-09-25
  10. AESO Announces Interim Approach to Large Load ConnectionsAlberta Electric System Operator · News release June 4, 2025; retrieved 2026-09-25
  11. Large Load ProjectsAlberta Electric System Operator · retrieved 2026-09-25
  12. Grid | AI Data Centres in AlbertaGovernment of Alberta · retrieved 2026-09-25
  13. Electrical permits for contractorsCity of Calgary · retrieved 2026-09-25
  14. Electrical codes and standardsGovernment of Alberta · retrieved 2026-09-25